Hello,
I am having issues with my installation. I have a large 400 amp panel with 4 live wires feeding the main panel, two red and two blue. I installed it with the help of an energy auditor, who said that the two red lines and two blue lines each feed a separate 200 amp service and since my HVAC was all on the left side of the panel, we clamped the two red lines.
However, it appears the total is significantly less than the sum of each 15 amp sensor, leading to a negative balance. Any suggestions?
Here are a couple pictures of the installation below.